Environmental Impact Assessment of 345kV Dongducheon CC-Yangju Transmission Line Construction Project

Environmental Impact Assessment of 345kV Dongducheon CC-Yangju Transmission Line Construction Project
Summary
 
Ordering organization
Client : Korea Electric Power Corporation
Term
Term : 2015.06.02 - 2017.05.21